CITIC Pacific's Australia iron ore delayed again

Updated: 2012-08-17 15:10
By China Daily ( China Daily)

CITIC Pacific Ltd, the conglomerate building the world's largest magnetite iron ore mine, said it has delayed production for at least the second time, hindered by Australia's safety standards and labor shortages.

Trial production will start in November instead of later this month, the Hong Kong-listed company said on Thursday in a statement. Difficulties include strict commissioning requirements in certification and safety standards, and a lack of technicians, it said.

CITIC Pacific's Australia iron ore delayed again

CITIC Pacific logo is displayed on paper documents. The conglomerate said on Thursday that it has delayed its Australia iron ore project for at least the second time, hindered by Australia's safety standards and labor shortages. [Photo/Agencies]

CITIC Pacific's $8 billion Sino Iron project has been beset by problems, including a more than four-fold blowout to the budget and currency hedging that cost HK$14.6 billion ($1.9 billion). The mine, being built by China Metallurgical Group Corp, was originally slated to begin output in the first half of 2011.

"It's a huge project and difficulties in planning, construction and transportation are well beyond our original preparation," CITIC Pacific Chairman Chang Zhenming said in Hong Kong on Thursday. The mine's total cost will be less than $10 billion, he said. The company had spent $7.8 billion on the mine by the end of June, Managing Director Zhang Jijing said on Thursday.

The Sino Iron project cost has risen to about $8 billion, Rob Cory, a spokesman for the company's Perth-based mining unit, said last month.

CITIC Pacific, the steelmaker and property group controlled by China's biggest state-owned investment company, said last July that it was delaying the mine's startup and revealed that costs had risen 35 percent more than expected.

"The commissioning process for an iron ore mine in Australia is very different from that in China," CITIC Pacific said in the statement. China Metallurgical Group Corp "is responsible for the processing area, which remains the primary cause of the delay," it said.

Australian mining magnate Clive Palmer sold the rights to the project to CITIC Pacific in 2007 for $200 million. Palmer stands to receive monthly royalty payments of $20 million from August, regardless of whether CITIC'S mine is in production, his private company Mineralogy Pty confirmed in an e-mail on Thursday.

CITIC Pacific reported a 9 percent decline in first-half profit to HK$5.48 billion on lower steel demand and property income. Profit from CITIC Pacific's steel unit declined 63 percent in the period.

"We expect the rest of 2012 will continue to be tough" for the steel business, the company said. Profit from the property unit in the mainland fell 68 percent from a year earlier, it said.

CITIC Pacific's profit also includes a HK$2.5 billion gain from its stake sale in CITIC Guoan and an investment property revaluation of HK$909 million, it said.

Bloomberg

 
8.03K
 
...
...
...
主站蜘蛛池模板: 亚洲男人的天堂久久香蕉 | 国产精品久久久久久久久久日本 | 久久久精品久久视频只有精品 | 福利姬在线精品观看 | 日本免费二区三区久久 | 综合久久一区二区三区 | 亚洲精品美女在线观看 | 手机毛片 | 国产一区二区三区在线观看免费 | 免费一级a毛片在线播放 | 久草在线视频在线观看 | 久久国产精品视频一区 | 国产精品久久久久久久网站 | 午夜一区二区福利视频在线 | 黄色一级毛片 | 久久国产视屏 | 久久99精品视香蕉蕉 | 色成人亚洲 | 一级特黄aaa大片在线观看 | 国产成人mv 在线播放 | 国产精品三 | 在线91精品国产免费 | 成人精品一区久久久久 | 337p粉嫩大胆噜噜噜鲁 | 成人免费一级在线播放 | 成人福利在线 | 欧美三级不卡在线观看视频 | 久久精品国产国产 | 一区二区三区免费高清视频 | 亚洲欧美精品一区 | 黄色毛片免费看 | 50岁老女人毛片一级亚洲 | 三级三级三级网站网址 | 国产精品免费看久久久香蕉 | 理论视频在线观看 | 国产一区二区三区欧美精品 | 亚欧成人中文字幕一区 | 寡妇野外啪啪一区二区 | 日本国产最新一区二区三区 | 久久在线观看免费视频 | 日韩亚洲一区中文字幕在线 |