Japan disaster plant's cold shutdown could face delay

Updated: 2011-08-18 08:16

(China Daily)

  Comments() Print Mail Large Medium  Small 分享按鈕 0

TOKYO - Tokyo Electric Power Co (TEPCO) said on Wednesday that it may fail in its bid to achieve "cold shutdown" at its tsunami-hit nuclear plant in Fukushima by January, as the world's worst nuclear crisis in 25 years rumbles on.

Efforts to decontaminate highly radioactive water at the facility have been delayed by repeated breakdowns of cesium absorption instruments, which have caused water leakage and malfunctioning of pumps, threatening to delay the process of stabilizing the stricken plant.

"It's possible that decontamination may not be completed as planned by the year-end, although we have not yet decided to change the target. That could affect the cold shutdown process," a company spokesman said.

His comments follow a similar statement on Tuesday, reported in the Nikkei business daily, from Junichi Matsumoto, a TEPCO spokesperson on nuclear issues.

Cold shutdown is usually defined as meaning the water in a reactor is below 100 C at normal atmospheric pressure, making its radioactive fuel safe from heating up again.

TEPCO also confirmed on Wednesday that it is testing a new radioactive water processing instrument as it struggles to cope with the damage wreaked by the 9.0-magnitude earthquake and tsunami that devastated the country's northeast coast in March.

With only an estimated 42,000 tons of highly contaminated water having been processed by Aug 9, roughly 120,000 tons are still left in the basement in turbine buildings and elsewhere.

TEPCO had set a goal of processing 200,000 tons of radioactive water by year-end since more water will be contaminated in the process of bringing the damaged reactors under control.

TEPCO officials and nuclear crisis minister Goshi Hosono were scheduled to hold a joint news conference on Wednesday to explain progress on work to bring the damaged reactors under control.

The test run of Toshiba Corp's cesium adsorption instrument, known as Sarry, is being carried out by running water with low-level radiation through equipment from French nuclear firm Areva SA and US nuclear waste management company Kurion Inc. It is scheduled to start operating fully as early as Thursday, Tepco officials said.

Sarry is relatively easy to maintain because it has fewer pumps, the breakdown of which have been a major reason for delays. Even if the system's overall operating rate holds steady at 90 percent, roughly 195,000 tons will be processed this year.

Reuters

Hot Topics

The European Central Bank (ECB) held a conference call late on Sunday ahead of the market opening, pledging the ECB will step in to buy eurozone bonds with efforts to forestall the euro zone's debt crisis from spreading.

主站蜘蛛池模板: 亚洲人成网7777777国产 | 欧美日韩综合精品一区二区三区 | 手机毛片在线 | 九九久久久 | 国产99视频精品免费视频免里 | 欧美另类69xxxxx视频 | 日韩精品麻豆 | 热99re久久精品这里都是免费 | 全高清特级毛片 | 国产三级在线观看播放 | 亚洲图片偷拍自拍 | 色久网站 | 久草视频网站 | 性日韩精品 | 欧美一区中文字幕 | 97在线观看完整免费 | 国产精品三级在线观看 | 国产日产亚洲系列首页 | 日韩一品在线播放视频一品免费 | 欧美一级日韩一级亚洲一级 | 日韩一级免费毛片 | 亚洲 欧美 日韩 丝袜 另类 | 亚洲欧美自拍偷拍 | 久草在线看 | 欧美日韩视频一区二区在线观看 | 一级毛片成人免费看免费不卡 | 国产一区二区三区久久小说 | 午夜精品影院 | 久久国产亚洲欧美日韩精品 | 亚洲综合性 | 久草视频在线网 | 亚洲一级毛片中文字幕 | 手机看片日韩日韩韩 | 日本不卡一区在线 | 国产精品福利午夜h视频 | 国产精品久久久久久久久久久久 | 日韩欧美在线一级一中文字暮 | 香蕉网影院在线观看免费 | 亚洲欧美精选 | 欧美成人做性视频在线播放 | 色偷偷亚洲男人天堂 |